09512 GPUs are installed and the vendor wants sign-off. Design the acceptance test.▼hardNewCoreWeaveMetaCrusoe4 repliesunlockedAcceptance is a contract document, not a checklist, so every criterion has to be a number with a tolerance that a vendor can be held to. Comparing nodes against each other rather than against a datasheet is what finds real defects, and the duration is what finds the thermal ones.Open full answer →
11Your new rack is tripping the contracted power limit during training. What do you do?▼hardNewCoreWeaveCrusoeMicrosoft4 replies○ sign inA training cluster is a synchronized load, so the peak is far above the average and the average is what everyone budgeted. The immediate mitigation takes minutes and costs a few percent of throughput, and the four durable fixes trade cost against throughput in different places.Open full answer →
35Your cluster is going into a colocation facility rather than your own building. What changes?▼mediumNewCoreWeaveLambda LabsCrusoe4 replies◆ premiumThe hardware is identical and almost everything around it moves: who can touch a node, how long a swap takes, what the contract actually guarantees, and what you can no longer measure. The six things to negotiate before signing and the two that decide whether operations work.Open full answer →